Dominion Energy has announced that its 2.6GW Coastal Virginia Offshore Wind (CVOW) project is 50% complete and on track for ...
The estimated cost of Dominion Energy’s 2.6-gigawatt Virginia Beach offshore wind farm has increased about 9%, which will ...
Dominion Energy said Coastal Virginia Offshore Wind project is 50% complete and remains on track for on-time completion at ...
Because of the latest cost update, the average residential customer using 1,000 kWh per month will see their bill go up by ...
Listen to this article Eggs aren’t the only thing getting more expensive. The estimated cost to build Dominion Energy’s Coastal Virginia Offshore Wind (CVOW) project has increased from $9.8 billion to ...
Dominion Energy has stated that the 2.6GW Coastal Virginia Offshore Wind (CVOW) project is now approximately 50% complete and ...
A gas leak has closed a stretch of road in Virginia Beach, according to a social post by Virginia Beach Police Department.
Hundreds of homes and businesses near Military Highway and Indian River Road are without power following a gas leak early ...
Port of Virginia’s Portsmouth Marine Terminal has welcomed the arrival of the first substation to be installed at the Coastal ...
Dominion Energy, a U.S. utility company, said that the estimated project costs of its Coastal Virginia off-shore wind farm had ...
Dominion Energy's 2.6 GW Coastal Virginia Offshore Wind (CVOW) project is now about 50% complete and remains on track for completion by the end of 2026. The project has created 2,000 direct and ...
Officials with Dominion Energy told the Richmond Times-Dispatch last week that the order will not affect its plans for a $9 ...